Screen Reader Access Skip to Main Content Font Size   Increase Font size Normal Font Decrease Font size
Indian Railway main logo
Search :
Find us on Facebook   Find us on Twitter Find us on Youtube View Content in Hindi
National Emblem of India

About Us

News & Recruitment Info

Tenders

Passenger Info

Kalka Shimla Railway Heritage Site

Contact Us

 
Bookmark Mail this page Print this page
QUICK LINKS
05-01-2018
“Infrastructure upgradation on war footing is our top priority”, says Shri Vishwesh Chaube, GM Northern Railway


Infrastructure upgradation o­n war footing is our top

priority”, says ShriVishweshChaube, GM Northern Railway.

Without disrupting running trains, Ten Bridges

were rehabilitated and repaired Following the

directives of ShriChaube by Moradabad Division

of Northern Railway within an extremely short

time period of 3 months that too without causing

any significant disturbance to movement of

running trains.

Shri Chaube created a systematic plan to do such major rehabilitation work by forming a team of multidisciplinary officers captained by their respective heads of Department. By keeping a very close watch o­n the entire exercise so that the allocated “Mega Block” time is not exceeded under any circumstances, ShriChaube ensured that the planned maintenance works were completed right down to the tightening the last nut o­n the tack fishplates.

Some of the important repair works completed recently o­n Laksar-Dehradun, Raiwala-Rishikesh and Moradabad-Saharanpur Sections:

·Provision of centralized bearings o­n Bridge no 3 (8x18.30 m plate girder) o­n Rishikesh-Raiwala Section.

·Replacement of rail cluster has been done with RCC slabs at Bridge no 134 (1x1.52 Rail cluster) o­n Laksar-Dehradun Section.

·Replacement of rail cluster with RCC slabs has been done o­n Bridge no 136(2x 1.38 Rail cluster) o­n Laksar-Dehradun Section.

·Rebuilding of bridge with RCC box segments has been undertaken o­n Down line Bridge no. 1215 (2X3.05 m) RCC slab o­n Moradabad-Saharanpur Section.

·Rebuilding of bridge with RCC box segments at Bridge no 1218 DN

(2X3.03m RCC slab) executed o­n Moradabad-Saharanpur Section.

·Yet another major bridge work was executed at Dhanetaand work o­n replacement of steel girders by PSC Slab o­n Bridge No. 899 was also completed using 100 MT Road Crane in running water stream o­n Rosa-Lucknow section during December 2017.

·Apart from these bridge repair works, staff and officers of Moradabad

Division also worked tirelessly towards completing work of Foot Over Bridge at Moradabad railway station as part of the safety agenda during last quarter.

·The Re-building of Bridge no 1218 DN (2x3.05m) with pre-cast RCC box segments at KM 1482/18-20 between Bundki and Nagina stations o­n Moradabad-Saharanpur DN line has also been successfully completed within a record time.

“Well executed maintenance work can o­nly be achieved by meticulous advance planning” said ShriChaube. During December 2017, ShriChaube guided officers of Moradabad division to undertake and complete the massive work of replacement of all four girders of a major bridge no. 1076 (4 x 12.2 m)in o­ne go alongwith replacement of bed blocks and centralized bearing– a feat that has not been seen in the recent past. This bridge, located at Dhaneta Railway Yard o­n the Moradabad-Lucknow section, carries all mainline mail express passenger and goods traffic. What is commendable is that the mammoth task of replacing the girders of this bridge was carried out in o­ne shot by deploying two high-capacitycranes and hundreds of skilled and semiskilled staff in strategically plannedsequence without exceeding the allocated time for “traffic Block” by even a minute.

In the recent maintenance works of these ten bridges, activities involving

dismantling of existing track, dismantling of abutments and central pier, removal of debris, laying of sand layer as levelling course, placement of pre-cast RCC slabs and box segments, Backfilling along with associated works namely backfilling cess repairs and then finally re-linking of re-laid tracks were done by gangs of workmen working with clockwork precision.

Especially remarkable is the fact that while the work of bridge repairs was being done, all the other track assets, signals and OHE structures o­n these affected lines were also concurrently repaired in what is known as “Shadow block”. Teams deployed in tandem for doing work in such a shadow block did complete track renewal of Point no-60/B in Nazibabad Yard, replaced a fractured rail at km 1509/6- 8 by welding it in-situ. These repairs alone removed a long-standing speed restriction o­n running of trains that had to be imposed due to degraded track. As a result, trains are now running o­n this section at faster speed.

Besides these, extensive repairs were done at MuzzampurNarain Yard by using heavy machinery and two rails were replaced o­n Bundki - Nagina block section using the opportunity of shadow blocks.

*





  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.