05-02-2025
Northern Railway State Wise Budget

Delhi

BudgetAllocation:(RsinCr)

#

Items

2009-14

2025-26

1

AnnualAverage

96

2,593

(27times)

Works(2014-25)

Newtracksconstructed:24 km

Electrified37kmsince2014.Delhiis100%electrified

Ongoingprojects(Newtracks):4projects;302km;4,778Cr

13AmritstationsofRs.5,887Crarebeingdeveloped

Kavach:(Fig.inRKm)

Work/Tenderinprogress

TotalSanctioned

30

128

14railflyovers&under-bridgesconstructedsince2014

Passengeramenitiesprovidedsince2014:

Lift:31

Escalator: 38

Wifi(NumberofStations):26

Running11VandeBharatcovering5districtshaving5unique stoppages in Delhi

1AmritBharatExpress(Darbhanga–AnandViharTerminal),covering

1districtshaving1uniquestoppagesinDelhi


13 stations will be developed asAmritstations:AdarshnagarDelhi, Anand Vihar, Bijwasan, Delhi, Delhi Cantt., Delhi Sarai Rohilla, Delhi Shahadra, Hazrat Nizamuddin, Narela, New Delhi, Sabzi Mandi, Safdarjung, Tilak Bridge

StationRedevelopmentProgress:

#

StationName

Cr

Status

1

Bijwasan

310

Tenderawardedon30.10.2019

The work is progressingwellwithmajor milestones like Ground floor and first floor slab work of station building completion. Concourse foundation, columns and slab above platforms are completed except for platform 6 and7. Externaldevelopment including STP and retaining walls, is advancing. Platform shelter and subway finishing works are in progress.

2

DelhiCantt.

371

Tenderawardedon18.06.2024.

The project progresses with soil investigation, barricading, and excavation underway. Approvals for drawings, structural designs, and Design Basis Reports forstaffquarters, Overhead Tanks, and the East Side Station Building have been secured. Construction of staff quarters has advanced to third-floor slab casting,and the East Side Station Building approach road, overhead tank and elevated road execution has started.

3

NewDelhi

4,744

Multimodal Transport Hub (MMTH): Work awarded o­n 14.06.24. Soil investigation, demolition of Gatiman lounge, railway club and JE office, survey for identification of utilities completed. The works of shifting of municipal drain, construction of guide wall is in progress. Work held up for want of tree felling, public transplantation permission from forest department. A meeting between VC/RLDAandPrincipalSecretary


#

StationName

Cr

Status

EnvironmentandForest,Delhiwas heldonDec'24toexpeditethe approval of tree felling/transplantation. Residentialblock:Workfor Residentialblockhavingtwotowers with 144 Qtr awarded o­n 23.07.24.The workforSoilinvestigation,surveyfor identificationofutilities,siteclearance anddismantlingofexistingstructures havebeencompleted.Designand drawingsareunderpreparation by the EPC contractor. Work held up for want oftreefelling,publictransplantation permission from forest department.

4

Safdarjang

385

Tenderawardedon23.12.2020

Station building structural work completed and finishing work is in progress. S&T building is completed andisinoperation.Operationalbuilding foundations and basements are progressing steadily. Air concourse foundations are complete at keypoints, with fabrication underway in Bangalore.

Total

5,810


(Annexure-A)

DELHI

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

1

Dayabasti-Gradeseparator

3km/359Cr

64%

2

AnandVihar-TilakBridge3rd&4thline

20km/419Cr

45%

3

Delhi-Sohna-Nuh-Ferozpur- Jhirka-Alwar

104km/2,500Cr

0

4

Delhi-Shamli-Tapriincluding Saharanpur by-pass

175km/1,500Cr

0%


Haryana

BudgetAllocation:(RsinCr)

#

Items

2009-14

2025-26

1

AnnualAverage

315

3,416

(11times)

Works(FiginKM)

#

Items

Averageperyear

2009-2014

2014-25

1

Newtracks

71

75

2

Electrification

9

121(13x)

100%electrified

Constructed823kmofnewtracksinHaryanasince2014whichis almost equal to the entire rail network of UAE

Electrified1,328kmsince2014.Haryanais100%electrified

Ongoingprojects(Newtracks):14projects;1,195km;15,875 Cr

34AmritstationsofRs.1,149Crarebeingdeveloped

Kavach:(Fig.inRKm)

Work/Tenderinprogress

TotalSanctioned

96

398

534railflyovers&under-bridgesconstructedsince2014

Passengeramenitiesprovidedsince2014:

Lift:6

Escalator:2

Wifi(NumberofStations):140

Running5VandeBharatcovering3districtshaving3uniquestoppages in Haryana


34 stations will be developed as Amrit stations : Ambala Cantt., Ambala City, Bahadurgarh, Ballabhgarh, Bhattu, Bhiwani Jn, Charkhi Dadri, Faridabad, Faridabad New Town, Gohana, Gurugram, Hansi, Hisar, Hodal, Jind Jn, Kalanwali, Kalka, Karnal, Kosli, Kurukshetra Jn, Loharu, Mahendragarh, Mandi Adampur, Mandi Dabwali, Narnaul, Narwana Jn, Palwal, Panipat Jn, Pataudi Road, Rewari, Rohtak, Sirsa, Sonipat, Yamunanagar Jagadhri

StationRedevelopmentProgress:

#

Station Name

Cr

Status

1.

Faridabad

262

Tenderawardedon19.08.2022.

West MLCP has five floors completed, with work o­n thesixthfloorandterraceongoing.EastMLCP has three floors completed, and work o­n terrace ongoing

East Station Building(G+1): Shifting of booking office and Dismantling of existing structures completed. Structural work is of station building completed and finishing work is in progress.

West Station Building(G+1): Structural work isof station building completed andfinishingworkis in progress.Refurbishment of existing buildings in progress.

FOBs: Foundations of North FOB completed except o­n Platform 2 & 3. Columns andfabrication of Girders inprogress.Foundationand column work of south FOB partially completed.

Concourse and Through Roof: Columns in progress in Non-Platform area. Foundation in progress in Platform area.

2.

Gurugram

295

Tenderawardedon07.06.2024

Temporary railway office construction and office shifting are completed. Demolition of the main station building and development of the automobile stacking area completed. Foundation work of Main Station Building, Air-concourse, Through roof and FOB and fabrication of FOB ,Air concourse and Station Building is in progress.

TotalCost

557


(Annexure-A)

Haryana

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

1

Chandigarh-Baddi

28km/1,540Cr

27%

2

ConnectivitybetweenPalwal and New Prithala

3.5km/66Cr

100%

3

Rewari-KhatuwasDoubling

27km/352Cr

25%

4

Bhiwani-Dobh-BahaliDoubling

42km/471Cr

20%

5

Doubling between Churu- Sadulpur BG Line Doubling betweenLuni-Samdari-Bhildi section

330km/3,554Cr

2%

6

DoublingbetweenManheru- Bawani

Khera

32km/413Cr

25%

7

DoublingbetweenKhatuwas- Narnaul

24km/313Cr

40%

8

Meerut-Panipat

104km/2,200Cr

1%

9

Delhi-Sohna-Nuh-Ferozpur- Jhirka- Alwar

104km/2,500Cr

0%

10

YamunaNagar-Chandigarhvia Sadhaura, Narayangarh

91km/901Cr

0%

11

Hissar-SirsaviaAgrohaand Fatehabad

93km/410Cr

0%

12

DoublingofPanipat-Rohtak

71km/714Cr

0%

13

DoublingofFirozpur-Bhatinda and Jakhal- Hisar

169km/1,688Cr

0%

14

DoublingofAsthalbohar-Rewari

75km/752Cr

0%


HimachalPradesh

BudgetAllocation:(RsinCr)

#

Items

2009-14

2025-26

1

AnnualAverage

108

2,716

(25times)

InHPnotrackkmwereaddedin2009-2014,whilesince2014,16.5km constructed.

Himachalis100percentelectrified.

Ongoingprojects(Newtracks):4projects;255km;13,168Cr

4AmritstationsofRs.45.5Crarebeingdeveloped

24railflyovers&under-bridgesconstructedsince2014

Passengeramenitiesprovidedsince2014:

Wifi(NumberofStations):24

Running1VandeBharatcovering1districtshaving2uniquestoppages in Himachal Pradesh


4stationswillbedevelopedasAmritstations:AmbAndaura, Baijnath Paprola, Palampur Himachal, Shimla

StationRedevelopmentProgress:

#

StationName

Cr

Status

1

AmbAnduara

23.84

The work of Improvement to facade and elevation, interiors, waiting halls, toilets, traffic circulation, beautification of circulating area, entrance porches, cover over platform, good quality durable furniture are completed.

12m wide roof plaza:Launchingof Girders have been completed. Foundation for Ramp and staircase in progress. Deck slab has been casted.

2

BaijnathPaprola

8.12

Structural work of the station completed.Plumbing, Sanitary and finishing workinsidebuilding, Circulating area, Parking in circulating area are in progress.

TotalCost

32


(Annexure-A)

HIMACHALPRADESH

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

1

Bhanupalli-Bilaspur-Beri

63km/

6,753 Cr

47%

2

Nangal Dam-Talwara & Taking over sidingofMukerian-Talwara(29.16km)

123km/

2,018 Cr

89%

3

Chandigarh-Baddi

28km/

1,540 Cr

475

4

Una-KunaPartofUna-Hamirpur

41km/

2,856 Cr

0%


Jammu&Kashmir

BudgetAllocation:(RsinCr)

#

Items

2009-14

2025-26

1

AnnualAverage

1,044

844

Commissioningduring2014-25

135kmnewtracksConstructedsince2014

Electrified344kmsince2014.against0kmduring2009-14.J&K

is100%electrified

Ongoingprojects(Newtracks):1project;272km;41,159Cr

4AmritstationsofRs.292.5Crarebeingdeveloped:Budgam, Jammu Tawi, Shri Mata Vaishno Devi Katra, Udhampur

06railflyovers&under-bridges

Passengeramenitiesprovidedsince2014:

Lift:5

Escalator:6

Wifi(NumberofStations):28

Running2VandeBharatcovering3districtshaving4uniquestoppages in Jammu & Kashmir


StationRedevelopmentProgress

#

StationName

Cr

Status

1

JammuTawi

259

Tenderawardedon17.08.2022

2nd Entry Station Building: Structural, plastering, and flooring works are done and finalfinishingin advanced stage. GRP building (G+2) frame is complete and finishing work is in progress. Girder launching work of roof plaza and FOBs ingreenfieldareainprogress and foundation and column work is in progress at other locations. The work of the minor bridge is completed. While external development, including drainage pipelines and retaining walls, is underway. HVAC, solar panels, and lift installations at 2nd entry are complete.

Main entry station Building: Design and drawings are complete, with utility shifting in progress.


(Annexure-A)

JAMMU&KASHMIR

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

1

Udhampur-Srinagar-Baramula

272km/41,159Cr

99%


Punjab

BudgetAllocation:(RsinCr)

#

Items

2009-14

2025-26

1

AnnualAverage

225

5,421

(24times)

Works(FiginKM)

#

Items

Averageperyear

2009-2014

2014-25

1

Newtracks

29

35

2

Electrification

33

149(4.5x)

100%electrified

Constructed 382 km of new tracks in Punjab since 2014 which ismore than the entire rail network of Philippines

Electrified1,634kmsince2014.Haryanais100%electrified.

Ongoingprojects(Newtracks):12projects;1,158km;19,843 Cr

30AmritstationsofRs.1,122Crarebeingdeveloped

Kavach:(Fig.inRKm)

Work/Tenderinprogress

TotalSanctioned

0

113

372railflyovers&under-bridgesconstructedsince2014

Passengeramenitiesprovidedsince2014:

Lift:8

Escalator:8

Wifi(NumberofStations):151

Running4VandeBharatcovering6districtshaving7uniquestoppages in Punjab


30 stations will be developed as Amrit stations : Abohar, Amritsar, Anandpur Sahib, Beas, Bhatinda Jn, Dhandari Kalan, Dhuri, Fazilka, Firozpur Cantt, Gurdaspur, Hoshiarpur, Jalandhar Cantt Jn, Jalandhar City Jn, Kapurthala, Kot Kapura Jn, Ludhiana Jn, Malerkotla, Mansa, Moga, Muktsar, Nangal Dam, Pathankot Cantt., PathankotCity,Patiala, Phagwara Jn, Phillaur Jn, Rup Nagar, Sangrur, SASN Mohali, Sirhind

StationRedevelopmentProgress:

#

StationName

Cr

Status

1

JalandharCantt

99

Tenderawardedon17.08.2022

Main station building structure up to the second floor is finished. Launching ofair concourse and FOBs girders completed and slab casted. FOB finishing work, cover over platform, platform surfacing, utilities work, art works and airconcourse through roof launching is in progress. Civil work for the secondentry building is at final stage.

2

Ludhiana

460

Tender awarded o­n 19.12.2022 FoundationsfortheG+5mainstation and G+2MultilevelCarParkingbuildings arecomplete,withongoingsteel structureframeerectionandfinishing work.MLCPstructuralworkis100% completeandfinishingworkisin progress.WestsideG+2secondentry buildingfoundationcompletedand structuralworkin progress. Piling, piers and pier caps work ofelevatedroadisin progress. Foundation work of roof plaza and FOB is in progress. Construction of quarters,resthouse,andhospitalis underway.

TotalCost

559


(Annexure-A)

PUNJAB

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

1

Bhanupalli-Bilaspur-Beri

63km/6,753Cr

47%

2

NangalDam-Talwara&Takingoversidingof Mukerian- Talwara(29.16 km)

123km/2,018Cr

89%

3

Rajpura-Bhatinda

173km/2,459Cr

100%

4

Doubling between Churu- Sadulpur BG Line DoublingbetweenLuni-Samdari-Bhildisection

3,554 Cr

5

Ferozpur-Patti

26km/300Cr

0%

6

Ludhiana-KilaRaipur(19Kms)withfreightline at Gill station o­n LDH-JHL section .

19km/238Cr

40%

7

Ludhiana-Mullanpur

21km/235Cr

92%

8

Mansa-Bhatinda(52Km)Ph.Iincludingnew MM for Rama Mandi( Raman)-Maur Mandi(Maur) via Talwandi Sabo( 29.11 km)

80km/449Cr

0%

9

Qadian-Beas

40km/842Cr

1%

10

YamunaNagar-ChandigarhviaSadhaura, Narayangarh

91km/901Cr

0%

11

Rajpura-Mohali

24km/406Cr

0%

12

DoublingofFirozpur-BhatindaandJakhal- Hisar

169km/1,688Cr

0%


Uttarakhand

BudgetAllocation:(RsinCr)

#

Items

2009-14

2025-26

1

AnnualAverage

187

4,641

(25times)

Commissioningduring2014-25:

Constructed69kmofnewtracksinUttarakhandsince 2014

Electrified303kmsince2014.Uttarakhandis100%electrified

Ongoingprojects(Newtracks):3projects;216km;25,941Cr

11AmritstationsofRs.147Crarebeingdeveloped

Dehradun,HaridwarJn.,Harrawala,KashipurJn,Kathgodam, Kichha, Kotdwar, Lal Kuan Jn, Ramnagar, Roorkee, Tanakpur

Kavach:(Fig.inRKm)

Work/Tenderinprogress

TotalSanctioned

0

49

100railflyovers&under-bridgesconstructedsince2014

Passengeramenitiesprovidedsince2014:

Lift:6

Escalator: 14

Wifi(NumberofStations):31

Running2VandeBharatcovering2districtshaving3uniquestoppages in Uttarakhand


(Annexure-A)

UTTARAKHAND

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

1

Rishikesh-Karanprayag

125km/24,659Cr

49%

2

Deoband(MuzzafarNagar)-Roorkee

27.5km/1,053Cr

96%

3

Kichha-Khatima

63km/228Cr

0%


UttarPradesh

BudgetAllocation:(RsinCr)

#

Items

2009-14

2025-26

1

AnnualAverage

1,109

19,858

(18times)

Works(FiginKM)

#

Items

Averageperyear

2009-2014

2014-25

1

Newtracks

199

474(2.4x)

2

Electrification

193

551(2.8x)

100%electrified

Constructed 5,209 km of new tracks in Uttar Pradesh since 2014which is almost equal to the entire rail network of Switzerland

Electrified6,064kmsince2014.UttarPradeshis100%electrified.

Ongoingprojects(Newtracks):70projects;5,958km;96,283 Cr

157AmritstationsofRs.7,695Crarebeingdeveloped

Kavach:(Fig.inRKm)

Work/Tenderinprogress

TotalSanctioned

2,043

4,876

1,568railflyovers&under-bridgesconstructedsince2014

Passengeramenitiesprovidedsince2014:

Lift:120

Escalator: 130

Wifi(NumberofStations):771

Running14VandeBharatcovering20districtshaving25unique stoppages in Uttar Pradesh

1AmritBharatExpress(Darbhanga–AnandViharTerminal),covering

10districtshaving10uniquestoppagesin UP


157 stations will be developed as Amrit stations : Achnera, Agra Cantt., Agra Fort, Aishbagh Jn, Akbarpur Jn, Aligarh, Amethi, Amroha, AnandNagarJn.,Aonla,AyodhyaDhamJunction,Azamgarh,Babatpur, Bachhrawan, Badaun, Badshahnagar, Badshahpur, Baheri, Bahraich, Balamau Jn., Ballia,Balrampur,Banaras,Banda,BarabankiJn,Bareilly, BareillyCity,Barhni,Basti,BeltharaRoad,Bhadohi,Bharatkund,Bhatni, Bhuteshwar, Bijnor, Bulandsahar, Chandauli Majhwar, Chandausi, Chilbila, Chitrakut dham karwi, Chopan, Chunar Jn., Daliganj, Darshannagar, Deoria Sadar, Dhampur, Dildarnagar, Etawah Jn., Farrukhabad,Fatehabad,Fatehpur,FatehpurSikri,Firozabad,Gajraula, Garhmukteshwar, Gauriganj, Ghatampur, Ghaziabad, Ghazipur City, Gola Gokarnath, Gomtinagar, Gonda, Gorakhpur, Govardhan, Govindpuri, Gursahaiganj, Haidergarh, Hapur, Hardoi, Hathras City, Idgah Agra Jn, Izzatnagar, Janghai Jn, Jaunpur City, Jaunpur Jn, Kannauj, Kanpur Anwarganj, Kanpur Bridge Left Bank, Kanpur Central, Kaptanganj Jn, Kasganj Jn, Kashi, Khalilabad, Khorason road, Khurja Jn., Kosi Kalan, Kunda Harnamganj, Lakhimpur, Lalganj, Lalitpur Jn, Lambhua, Lohta, Lucknow (Charbagh) NR, Lucknow city, Lucknow Jn. (NER), Maghar, Mahoba Jn, Mailani Jn, Mainpuri Jn, Malhaur, Manak Nagar, Manikpur Jn, Mariahu, Mathura Jn, Mau Jn, Meerut City Jn, Mirzapur, Modinagar, Mohanlalganj, Moradabad Jn, Muzaffarnagar, Nagina, Najibabad Jn, Nihalgarh, Orai, Panki Dham, Phaphamau Jn, Phulpur,PilibhitJn,Pokhrayan,PratapgarhJn,PrayagJn,PrayagrajJn, Pt. Deen Dayal Upadhyay Jn , Rae Bareli Jn, Raja Ki Mandi, Ramghat Halt, Rampur Jn, Renukoot, Saharanpur Jn., Salempur, Seohara, Shahganj Jn, Shahjahanpur, Shamli, Shikohabad Jn., Shivpur, Siddharth nagar, Sitapur Jn., Sonbhadra, Sri Krishna Nagar, Sultanpur Jn, Suraimanpur, Swaminarayan Chappia, Takia, Tulsipur, Tundla Jn., Ujhani, Unchahar, Unnao Jn, Utraitia Jn, VaranasiCantt.,VaranasiCity, Vindhyachal, Virangana Lakshmibai, Vyasnagar, Zafarabad


StationRedevelopmentProgress:

#

Name

Cr

Status

1

Ayodhya Dham

Phase 1:

329.83

+

Phase 2:

422

Phase1:

Tenderawardedon07.03.2018

The station building, roof plaza, staff quarters, STP, substation, UG tank, parking, gates, extended porch, slip road, widening and extension of PF 2/ 3and other amenitiesatAyodhyaRailwayStation have been completed. Toilet block work o­n the platforms and roof plaza have alsobeen completed, (All works completed 100%.)

Phase 2:

Special Railway project status has been accorded through gazette notification issued o­n 04.01.2024. SLAO and arbitrator have been appointed by Govt. of UP o­n 12.04.2024. Notification under section 20A for acquisition of private land issued o­n 05.06.2024. Working permission o­nnazul land required for development of 2nd entry has been given. Railway boundary layout marked o­n ground jointly with revenue department and process of landacquisition is underway.

2

Gomtinagar

379

Tenderawardedon21.05.2018

The North Terminal station Building, air concourse structural andfinishingworkhas been completed withassociatedpassenger amenities. TwoCommercialblocks(R1and R2) structural work completed including basement parking, and finishing and utility works are in advanced stage. Station approach road work including lighting and drainage, boundary, horticultureworkarein advanced stage. Utility block such as AC plant room, STP, UGwatertank,substation etc. are in advanced stage. South terminal station building (second entry)-structural and external finishing work, platform surfacing and platform shelter work is in progress.


#

Name

Cr

Status

3

Lucknow (Charbagh)

494

Tenderawardedon31.07.2022

The Rear Station Building (second entry, G+6) structural framework completed up to 5th floor and 6th floor in progress alongwith block work, internal plaster and MEP. The concourse and PF 10/11 works is in the initialstagesofprogress.TheTTERest House and Dy. CMM/Store Depot have been completed.

4

MeerutCity

253

EPC tender has been opened o­n 02.01.2025 and offers are underevaluation.

5

Prayagraj

960

Tenderawardedon08.12.2022

Civil line side Station building(secondentry) workof3rdand4thfloorworkandits finishingworkisinprogress.RMS&arrival, parcel & arrival buildings and basement plaza(civil line) completed. Extension work of FOB-2 is also completed. Substation building, PF 7/8 structural steel work is in progress.

6

Ghaziabad

337

Tenderawardedon13.12.2022

Structural work of Station building city side (main entry) and Vijaynagar side (second entry) is in progress at basement roof slab level and column casting above basement roof slab. Foundational work of FOB, air concourse and through roof is in progress. STTC hostel finishing and flooring work isin progressandstaffquarterstructuralwork in progress.Other buildings such as sub station (both sides), Magistrate building, GRP and RPF building work is in progress.

7

Kanpur Central

767

Tenderawardedon05.06.2023

City side station and commercial building blocks basement work, driver lobby, substation building (city side and Cantt, side), podium plaza (city side) works are in progress.

8

Kashi

366

Tenderawardedon16.08.2023

Sitemobilizationhasbeencompleted.


#

Name

Cr

Status

Foundationworkof station building o­n the North and south side is in progress.

9

Gorakhpur

509

Tenderawardedon27.12.2023

Work of new laundry at GF roof slab level, Structural work of substation, pay and use toilet, GRP thana, coolie rest house and MLCP foundation and columns , FOB work are in progress.

10

Virangana Lakshmibai

450

Tenderawardedon05.07.2024.

Survey, Geotechnical investigation completed and existing old structures removed from proposed site of-RMC, GRP Thana, Subordinate rest house, Union office, Junior High school. Utility shifting is in progress also.

Total

5,267


(Annexure-A)

UTTARPRADESH

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

1

Jhansi-Khairar-Manikpur&Khirar-Bhimsen

431km/4,330Cr

32%

2

Lalitpur-Satna,Rewa-Singrauli& Mahoba- Khajuraho

541km/8,914Cr

43%

3

AnandNagar-Ghughli

53km/958Cr

40%

4

Bahraich & Khalilabad via Binga, Shravasti, Balrampur,Utraula,Domariyaganj,Mehdawal, Bansi new BG Line

240km/4,940Cr

18%

5

Bhatni-Aunriharwithelectrification(125Kms) excluding Indara-

Mau(116.95Km)

117km/2,529Cr

84%

6

Mathura-Jhansi3rdline

274km/5,190Cr

90%

7

Deoband(Muzaffarnagar)-Roorkee

27km/1,053Cr

96%

8

Mughalsarai-Allahabad,3rdline

150km/2,649Cr

42%

9

Mailani-Nanpara

1,708 Cr

10

Janghai-Phaphamauwithelectrification

47km/414Cr

100%

11

Allahabad-Bamrauli4thline(10Km)withflying over at Subedarganj

10km/494Cr

47%

12

BurhwalGonda3rdline

62km/800Cr

87%

13

Janghai-Pratapgarh-Amethi

87km/719Cr

83%

14

Sahjanwa-Dohrighat

81km/1,320Cr

32%

15

AgraFortandBandikui

150km/988Cr

11%

16

Lalitpur-BirariwithflyoveratLalitpur

16km/304Cr

45%

17

DoublingofBilli-Chunar

102km/1,424Cr

0%

18

Phephna-Indara,Mau-Shahganjdoubling excluding Indara-Mau

150km/1,529Cr

93%


UTTARPRADESH

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

19

Ramna-Singrauli

160km/2,436Cr

0%

20

ByepassatSainthia(5Km),Sitarampur(7Km), Mughalsarai, Allahabad, Etawah (11 Km)

24km/831Cr

17%

21

AligarhFlyover

22km/1,179Cr

8%

22

DoublingofGorakhpur-Valmikinagar

96km/1,121Cr

4%

23

Varanasi-Madhosingh-Allahabad

120km/2,018Cr

100%

24

Jhansi-Bina3rdline

153km/2,002Cr

85%

25

KarailaRoad-Shaktinagar

32km/763Cr

100%

26

Barabanki-Malhaur-3rd&4thLine(32.84 km)

33km/407Cr

63%

27

Aligarh-DaudKhan3rdline&constructionof flyover at Daud khan

18km/452Cr

32%

28

Bhandai-FlyoverforEtawahbounddowntrain (10 Km)

10km/186Cr

8%

29

Mau-Ghazipur-Tarighat

51km/1,766Cr

68%

30

Dailwara-Berari-ChordLine(5.2km)

5.2km/77Cr

100%

31

Domingarh-Gorakhpur-Gorakhpur Cantt.-Kusumhi-3rdrunninglineand

Gorakhpur-NakahaJungleDoubling(21.15km)

21km/508Cr

95%

32

Chhapra-BalliaPatchDoubling(65km)

65km/937Cr

99%

33

Chipyana-Buzurg(CYZ)-Ghaziabad(GZB)

2.5km/15Cr

5%

34

DoublingbetweenJaunpurJn.-Zaffarabad(6.3 Km)

6.3km/177Cr

3%

35

YamunaBr-AgraFort-DoublelinewithMajor Bridge at Yamuna river

2.5km/122Cr

90%

36

Mathura-Vrindavan

11km/403Cr

5%

37

Chhitauni-TamkuhiRoad

59km/895Cr

49%


UTTARPRADESH

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

38

Surface Triangle Line between Bhadaura StationandKarmaStation(Dildarnagar-Tarighat Line)

11km/200Cr

28%

39

Utretia-Zafrabad - Doubling of balance 148 km section with MMs for Rae Bareli - Akbarganj (46.9 km) & Sultanpur - Amethi (29.22 km) with newMMofSultanpur-Kadipur(38.7km)-new lines

263km/1,582Cr

72%

40

Etah-Kasganj

29km/389Cr

0%

41

Varanasi-Mughalsarai-3rdline(16.72km)with substructure of two lines o­n Bridge no.-11 (Malviya Bridge)

16.7km/1,350Cr

0%

42

4thlinebetweenPankidham-GMC

2km/18Cr

10%

43

ByepasslineatAyodhya

1.5km/56Cr

0%

44

Bareily-Chandausi-AligarhDL

168km/2,227Cr

0%

45

Meerut-Panipat

104km/2,200Cr

1%

46

Chord line connecting Muftiganj (MFJ) - Jaunpur(JNU)-MGWNbypassingJaunpur(1.5 Km)

1.5km/76Cr

0%

47

Chord line connecting Didarganj (DJD) - Shahganj(SHG)-Bilwai(BWI)bypassing Shahganj

5.7km/137Cr

0%

48

RobertsganjtoMughalsaraiviaMadhupur, Sukrit, Ahrora

78km/1,260Cr

0%

49

Hathua-Bhatni

80km/277Cr

87%

50

Kapilvastu-Basti

91km/644Cr

0%

51

Padrauna-KushinagarviaGorakhpur

64.5km/1,345Cr

0%

52

Unchhar-Amethi

66km/1,229Cr

24%


UTTARPRADESH

#

NameofProject

Length(Km)/ Cost (Cr)

Progress (%)

53

Faizabad-LalganjviaRaibareilly

116km/664Cr

0%

54

HardoitoGursahaiganjviaSandi

59km/1,302Cr

0%

55

Bahraich-Nanpara-NepalGanj

56km/342Cr

55%

56

Iradatganj-KunwahdihConstructionofFlyover

23km/2,730Cr

0%

57

Karchhana-IradatganjConstructionofFlyover

13km/563Cr

0%

58

Naini-IrdatganjConstructionofFlyover

13km/676Cr

0%

59

JeonathpurFlyover

10km/739Cr

0%

60

Mathura-Mureshi-RampurFlyoverforavoiding surface crossing at Mathura

11km/210Cr

0%

61

AllahabadDivision.ConstructionofKanpur flyover.

30km/1,791Cr

0%

62

Mathura-Dholpur-4thline

107km/2,947Cr

0%

63

DholpurJhansi-Bina-4thline.

322km/4,871Cr

0%

64

Delhi-Shamli-TapriincludingSaharanpur by-pass

175km/1,500Cr

0%

65

PhaphamautoUnnnaoviaKundaHarnamganj

184km/1,600Cr

0%

66

Varanasi-MoradabadbypassingLucknowwith fly over at Unnao

100km/2,000Cr

0%

67

DoublingofMoradabad-Chandausi

44km/440Cr

0%

68

Constructionof3"linebetweenVaranasi Shivpur (5.83 Km)

5.8km/76Cr

0%






  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.