Key Targets/Objectives:
Key targets achieved by the electrical department in 2021-22:
Power Supply:
S. No. | Description | Target | Progress |
1. | Rewiring of service buildings | 10 Nos. | 13 Nos. |
2. | Power factor improvement to unity at those locations where the units of energy in KVAH (Nos. of sub-station) | 8 Nos. | 9 Nos. |
3. | Provision of LED based station name boards | 4 Nos. | 4 Nos. |
4. | Provision of 5 star rating pump sets (upto 20 HP) | 100 Nos. | 57 Nos. |
5. | Provision of escalators | 4 Nos. | 2 Nos. |
Coaching:
S. No. | Description | Target | Progress |
1. | Punctuality loss on Electrical account | 0.51 | 0.43 |
2. | Enroute coach detachment | 0 | 0 |
3. | Provision of 630 Amp Interlocking HOG contactor in Power cars | 14 Nos. | 14 Nos. |
4. | Provision of safety chains for ZS coupler of LHB coaches | 1024 Nos. | 1024 Nos. |
5. | Railmadad outstanding satisfactory feedback from customers | More than 90% | 91.22% |