Key Targets and Objectives:-
S.N. | Work | Proposed Target for 2022-23 | Achievement (till Sep-22) | Action Plan |
1 | Energy consumption (MUs) | 35.5 | 21.58 | • Use of LEDs only for Illumination •Use of BEE rated equipments like Acs, Geysers. •Regular behavior change and awareness campaign •Replacement of Overhead lines with Cables to reduce AT&C losses. |
2 | Fuel efficiency i.e. saving of HSD oil (in Ltrs) by improvement of power supply reliability | 1,24,300 | 65,680 | • Regular chasing with UPPCL, UPCL in case of supply failure •Improving backbone electrical infrastructure to reduce internal failures |
3 | Provision of Lifts (Nos). SPN-2 nos in coordination with Constt. | 2 | NIL | Provision of lifts at SPN is not feasible with existing FOB. Work awarded for 01 lift at MB. |
4 | Provision of Escalators (Nos) DDN-2 & SPN-2 nos in coordination with constt. | 4 | NIL | LOA awarded of electric work for installation of 2 nos escalator at DDN and provision of escalators at SPN is not feasible with existing FOB |
5 | 5 MWp Grid connected solar plant by REMCL (MWp) over Moradabad division. | 1.371 | 1.143 | 1143 KWp has been installed. |
7 | Running of Nanda Devi 12401/02,12056/55 (Jan Shatabdi Express) & Ujjain/Indore Express(14309/10/17/18) with HOG | 6 | 6 | All rakes of these trains running with HOG |