Achievements on targeted work:
S. N. | Item | Unit | Target 2022-23 | Progress 2022-23 up to Oct 2022 | % Achieved |
1 | Replacement of overage Signaling Gears | | | | |
a) | Mechanical Lever frames | Nos. | 1 | 0 | 0% |
b) | Point Machine | Nos. | 228 | 111 | 49% |
c) | LED Signals | Nos. | 1000 | 633 | 63% |
d) | BPAC (UAC) | Block Sections | 20 | 11 | 55% |
2 | Installation of Thick web Switch | Nos. | 110 | 69 | 63% |
3 | Provision of Sliding booms at LC Gate | Nos. | 50 | 14 | 28% |
4 | Block working media redundancy by OFC & Quad | Block Sections | 45 | 14 | 31% |
5 | Provision of Dual detection in block working | Block Sections | 49 | 12 | 24% |
6 | Provision of Fire Alarm in Relay Rooms | Nos. | 25 | 30 | 120% |
7 | Provision of IPS at LC gates | Nos. | 7 | 5 | 71% |
8 | Overhauling of Block Instruments | Nos. | 24 | 5 | 21% |
a) | NTI | Nos. | 14 | 4 | 29% |
b) | SGE | Nos. | 2 | 2 | 100% |
c) | TLI | Nos. | 8 | 5 | 63% |