Key Targets / Objectives:
ØMAJOR ACTION PLAN DIVISIONAL MAINTENANCE TARGET(TRD):
S. N. | ITEMS | Target 2021-22 | Cumulative Progress since Apr’ 21 |
1 | IOH of OHE (in TKM) | 952 | 1072 |
2 | AOH of ATD (in Nos.) | 2544 | 2544 |
3 | AOH of gantries (in Nos.) | 55 | 55 |
4 | Checking of T-outs & X-Overs (in Nos.) | 1390 | 1390 |
5 | POH of ATD (in Nos.) | 371 | 389 |
ØMAJOR ACTION PLAN DIVISIONAL MAINTENANCE TARGET(RSO):
S. N. | Activity | Target 2021-22 | Cumulative since Apr’ 21 |
1 | %age of Energy Regeneration |
1.1 | Coaching trains | 17.00% | 17.80% |
1.2 | Freight trains | 12.00% | 12.05% |
2 | Maintenance Management of Trip Shed |
2.1 | No. of TI of coaching locos/month | 450 | 455 |
2.2 | No. of TI of freight locos/month | 60 | 84 |
ØELECTRIFICATION TARGETS (2021-2022)
S. N. | Section | RKM | Executing Agency | Progress |
1. | Lohian Khas (Incl)-Nakodar (Excl) | 32 | RE/UMB | CRS inspection done. |
2. | Nakodar (incl)-Philaur (Excl) | 33 |
3. | Jalandhar City(Excl)-Nakodar (Excl) | 30 |
4. | Budgam – Baramulla | 50 | IRCON/USBRL |
ØELECTRIFICATION TARGETS (2022-23)
SN. | Section | RKM | Executing Agency |
1. | Banihal-Budgam | 88 | USBRL/IRCON |
2. | Bathinda - Kotkapura | 42 | RITES |
3. | Kotakapura – Firozpur | 45 | RITES |
4. | Jalandhar City – Lohian Khas | 52 | RE/FZR |
5. | Ludhiana – Moga | 69 |
6. | Jagraon – Firozpur – HussainiWala | 91 |
7. | Firozpur City – Fazilka | 85 |
8. | Fazilka – Abohar | 43 |
9. | Kotkapura – Fazilka | 80 |
10. | TaranTaran-Patti-Khemkaran | 54 |
11. | Phagwara – Nawan Shahar – Jaijon Doaba (incl. Rahon) | 74 |
12. | Jalandhar Cantt – Hoshiarpur | 38 |
13. | Verka – Derababa Nanak | 45 |
14. | Chheharta – Attari | 20 | RE/UMB |
ØELECTRIFICATION TARGETS (2023-24)
SN. | Section | RKM | Executing Agency |
1. | Moga – Firozpur | 55 | RE/FZR |
2. | Lohian Khas – Firozpur | 65 |