Key Targets/Progress |
| S.No. | Items | Unit | Annual Target 2021-22 | Progress for the month of Mar-22 | Cumulative Progress up to Mar-22 | Remarks |
| 1 | TRR (P) | Tkm | 106.8 | 6.432 | 68.410 | |
| 2 | TSR (P) | Km | 78.8 | 10.307 | 45.724 | |
| 3 | TRR (S) | Tkm | 28.75 | 17.750 | 49.160 | Target completed. |
| 4 | TSR (S) | Km | 24.5 | 17.766 | 36.571 | Target completed. |
| 5 | CTR (P+S) | CTR unit | 119.43 | 25.905 | 99.933 | |
| 6 | Deep Screening of Plain Track | KM | 170 | 32.981 | 135.200 | |
| 7 | Deep Screening of turnouts | Nos. | 171 | 48 | 235 | Target completed. |
| 8 | Shoulder Ballast Cleaning | KM | 300 | 17.103 | 316.654 | Target completed. |
| 9 | TTR | Eq. Nos | 144 | 17.75 | 176.75 | Target completed. |
| 10 | TWS | Nos. | 30 | 7 | 46 | Target completed. |
| 11 | TWR | KM | 29 | 1.608 | 24.671 | |
| 12 | FBWP | Nos. | - | 901 | 9450 | |
| 13 | TBR | KM | - | 3.545 | 62.276 | |
| 14 | TFR | KM | 250 | 18.610 | 291.890 | Target completed. |
| 15 | TBSR | Nos. | 2323 | 0 | 0 | |
| 16 | Rectification of defective layout in Yards (No. of | Nos. | 20 | 0 | 16 | |
| 17 | Ballast Supply | Lakh Cum | 2.32 | 0.345 | 1.57 | Including Cess supply |
| 18 | Ballast Inserted | Lakh Cum | 2.32 | 0.184 | 1.440 | |
| 19 | Raising of sectional Speed | Route Km | 232.19 | | 106.890 | Proposal of PHR-LNK =64.10Km, JRC-HSX=38.22Km, Total= 76.32 km Sent to HQ. |
| 20 | Raising of loop line speed to 30Kmph | Route Km | 420.42 | 42.9 | 42.9 | Proposal of ASR-PTK =106Km, and ASR-KEMK =77Km, Total= 183 km Sent to HQ. |
| 21 | Relaxation of PSR | Nos. | 0 | 0 | 0 | |
| 22 | Removal of PSR | Nos. | 6 | 1 | 6 | |
| 23 | Toe load measurement | TKM | 0 | 25.42 | 220.42 | |
| 24 | Painting of rail | TKM | 0 | 6.432 | 108.488 | |
| 25 | Installation of Way side lubricator | Nos. | 10 | 0 | 10 | Target completed. |
| | | | | | | |