1 | Rewiring of quarters (Nos.) | 300 | 43 | 175 | 219 | Work under progress |
2 | Rewiring of service buildings (Nos.) | 20 | 3 | 12 | 31 | Annual target achieved |
3 | Energy consumption including DISCOM, Solar generation and DG sets Generation (KWH/KW/Month) | 41.42 | 3.70 | 24.16 | 24.03 | |
4 | Specific Energy consumption including DISCOM, Solar generation and DG sets Generation (KWH/KW/Month) | 101.39 | 94.15 | 101.39 | 87.32 | |
5 | HSD oil consumption (in Liters) up to Feb.24 | 54000 | 5905.5 | 31500 | 44013.4 | |
6 | Power factor improvement to unity at those locations where the units of energy in KVAH (Nos. of sub-station) | 5 | 0 | 3 | 0 | Estimate under vetting |
7 | Energy Audit External (Nos.) | 2 | 0 | 1 | 0 | Tender under TC |
8 | Use of Façade lighting with LEDs (Nos) | 2 | 0 | 1 | 0 | Work will be done under ABSS. Tender awarded for 15 stations |
9 | Provision of LED based station name boards (Nos) | 5 | 2 | 3 | 2 | Balance quantity is being covered under ABSS works |
10 | Automation of Pumping installations with GSM technique (Nos) | 50 | 0 | 30 | 0 | Work will be done under IR-Niyantrac. Abstract estimate under vetting |
11 | Provision of 5 Star rating pump sets (up to 20 HP). (nos) | 25 | 3 | 15 | 20 | Proportionate target achieved |
12 | Provision of Lifts (Nos) | 3 | 0 | 2 | 0 | Will be done under ABSS work. |
13 | Provision of Escalators (Nos) BTI-4 nos & SIR-02 | 6 | 0 | 4 | 0 | Escalators surrendered |
14 | Provision of grid connected solar plant (KWP) | 500 | 0 | 290 | 0 | Tender discharged and retendering done. Tender to be opened on 17.11.2023 |
15 | Joint water supply signed by Sr. DEE & Sr. DEN. Stations to be decided in consultation with Sr. DEN | 3 | 0 | 2 | 0 | Under progress |
16 | Replacement of Overhead conductors with Underground cables.(no. of locations) | 5 | 0 | 3 | 4 | Proportionate target achieved |
17 | Replacement of Non star rated split/ window AC's with 3 star and above AC's on age cum condition basis. | 50 | 2 | 30 | 62 | Annual target achieved |
18 | Joint checking of RRI at Sr. DEE’s level with S&T once in a year. (nos) | 1 | 0 | 1 | 0 | |
19 | Solar Units Generation per KWP/year (KWh) | 1250 | 67.04 | 729.16 | 692.79 | |
20 | Provision of 5 Star rating equipment by venders at Railway station (Nos. of stations) | 5 | 0 | 3 | 5 | Annual target achieved |
21 | Net Zero Station (Nos.) | 2 | 0 | 1 | 1 | SML |
22 | Adoption of smart prepaid metering system for all Railway Installations from which Railways has to collect charges for consumption electricity.(Nos.) | 14000 | 0 | 8165 | 0 | Work proposed under work program 2024-25(Vol-II) railway board power |
23 | To declare Railway station buildings and Railway office/Hospital buildings as Green buildings(Nos.) | 2 | 0 | 1 | 0 | Solar already installed at every feasible stations.Major part of work for achieving green building is from engineering side |
24 | Automatic Switching OFF/ON of Platforms Light for all A1/A category railwayStations (70% & 30% Circuit) | 5 | 0 | 3 | 1 | Work will be done under IR-Niyantrac. Abstract estimate under vetting |
25 | Replacement of Conventional fans with BLDC fans (Nos.) | 1000 | 0 | 583 | 0 | Estimate under vetting |
26 | Provision of solar panel at station ( no. of station) | 10 | 0 | 6 | 0 | Tender discharged and retendering done. Tender to be opened on 17.11.2023 |
27 | Safety audit (as per RB instructions) Nos. | 15 | 1 | 8 | 10 | Proportionate target achieved |