4.0 ACHIEVEMENTS OF S&T FOR THE YEAR 2024-till date
Signaling:
1. Pilu Khera has been commissioned on 10.04.2024.
· Electronic Interlocking (centralized) of M/s Kyosan has been provided with 24 nos. of routes along with dual VDU.
· 01 nos. of IPS of M/s Statcon has been provided.
· 01 nos. of Efftronics make Datalogger has been provided.
· UFSBI (Single Line)with HASSDAC has been provided in between PPDE-PKDE section.
2. Jind city has been commissioned on 08.06.2024.
· Electronic Interlocking (centralized) of M/s Kyosan has been provided with 38 nos. of routes along with dual VDU.
· 01 nos. of IPS of M/s Statcon has been provided.
· 01 nos. of Efftronics make Datalogger has been provided.
· UFSBI (Single Line)with HASSDAC has been provided in between JHI-JCY & JCY- PPDE section.
3. Madlauda has been commissioned on 04.08.2024.
· Electronic Interlocking (centralized) of M/s Kyosan has been provided with 24 nos. of routes along with dual VDU.
· 01 nos. of IPS of M/s Statcon has been provided.
· 01 nos. of Efftronics make Datalogger has been provided.
· UFSBI (Single Line)with HASSDAC has been provided in between MLDE-BHUL section.
4. Naulatha has been commissioned on 23.11.2024.
· Electronic Interlocking (centralized) of M/s Kyosan has been provided with 36 nos. of routes along with dual VDU.
· 01 nos. of IPS of M/s Statcon has been provided.
· 01 nos. of Efftronics make Datalogger has been provided.
· UFSBI (Single Line)with HASSDAC has been provided in between NLH-PNP section.
5. Shakur Basti has been commissioned on 16.01.2024.
· Electronic Interlocking (Distributed) of M/s Medha has been provided with 493 nos. of routes along with dual VDU.
· 04 nos. of IPS of M/s Statcon has been provided.
· 01 nos. of Efftronics make Datalogger has been provided.
· SGE (Double Line)with HASSDAC has been provided in between SSB-NNO section.
6. Nanauta has been commissioned on 05.02.2024.
· Electronic Interlocking (centralized) of M/s Kyosan has been provided with 27 nos. of routes along with dual VDU.
· 04 nos. of IPS of M/s Statcon has been provided.
· 01 nos. of Efftronics make Datalogger has been provided.
7. Karnal has been commissioned on 21.05.2025.
· Electronic Interlocking (centralized) of M/s Medha has been provided with 52 nos. of routes along with dual VDU.
· 02 nos. of IPS of M/s HBL has been provided.
· 01 nos. of Efftronics make Datalogger has been provided.
8. Delhi Sarai Rohilla has been commissioned on 28.07.2025.
· Electronic Interlocking (Distributed) of M/s Medha has been provided with 164 nos. of routes along with dual VDU.
· 03 nos. of IPS of M/s AMARA RAJA has been provided.
· 03 nos. of Efftronics make Datalogger has been provided