Key targets/Objectives


Achievements on targeted work:

S. N.

Item

Unit

Target 2022-23

Progress
2022-23 up to May 2022

% Achieved

1

Replacement of overage Signaling Gears

 

 

 

 

a)

Mechanical Lever frames

Nos.

1

0

0%

b)

Point Machine

 Nos.

228

24

11%

c)

LED Signals

Nos.

1000

125

13%

d)

BPAC (UAC)

Block Sections

20

7

35%

2

Installation of Thick web Switch

Nos.

110

13

12%

3

Provision of Sliding booms at LC Gate

Nos.

50

2

4%

4

Block working media redundancy by OFC & Quad

Block Sections

45

8

18%

5

Provision of Dual detection in block working

Block Sections

49

7

14%

6

Provision of Fire Alarm in Relay Rooms

Nos.

25

0

0%

7

Provision of IPS at LC gates

Nos.

7

1

14%

8

Overhauling of Block Instruments

Nos.

24

0

0%

a)

NTI

Nos.

14

0

0%

b)

SGE

Nos.

2

1

50%

c)

TLI

Nos.

8

0

0%


S&T failures in 2021-22 and mitigation action plan for year 2022-23:

Gears

% Contribution

Remark

BI

29.32%

1. Replacement of overaged BPAC is in progress, Target is for 25 block section in 2022-23 against scope of 30, 7 block sections have been commissioned till date.
2. Provision of redundancy is in progress for following aspects:
a) Power supply redundancy - separate DC-DC converters will be provided for each unit of dual detection
b) Power cable redundancy - separate cable carrying power supply to each unit of dual detection will be provided
c) Media redundancy - Block working will be provided on OFC & Quad both along with auto switch over
3. Work have been floated for 76 Nos SSDAC for provision of dual detection in block circuits
4. Procurement of spares: Spare cards for DAC and UFSBI are being procured via indenting for quick restoration of failure
5. Testing of Block media is being monitored on weekly basis. 25 bad sections have been identified and cable improvement work is in progress, 5 sections have been completed till date

BPAC

15.11%

HASSDAC

1.80%

NTI

0.78%

SGE

1.40%

SSDAC

6.88%

TLI

1.42%

UFSBI

1.94%

LC

8.42%

1. Provision of SLB: SLB are being provided on all interlocked LC gates, target for 2022-23 is of 50 LC gates against scope of 83. Work is awarded for all LC gates.
2. Replacement of MLB by ELB: ELB is being provided at LC gates with MLB where power source is available. For balance LC gates, provision of power supply is being chased with electric department
3. Purchasing of ELB spares by using imprest money for periodical replacement and failure rectification is being done.

ELEC

4.17%

MECH

4.25%

PT

13.99%

1. Replacement of overaged point machine is being done, Scope & target for year 2022-23 is 228 out of which 24 have been completed. Material is available and target will be achieved.
2. Pending deficiencies of point and crossing joint inspection is being highlighted and discussed with ENGG officers on weekly basis in Divisional safety meeting and action plan for compliance is planned and followed

ELEC

10.18%

MECH

3.81%

SIG

28.44%

1. ELD faults are being monitored on daily basis and weekly report is generated at individual SI level to identify the stations with poor progress, ELD faults are being attended and rectified on priority.
2. Datalogger exception report is generated and uploaded on Mark-3 App on daily basis where sectional staff take action and update progress of the same on the App. Sectional and divisional officers monitor the same on daily basis to prevent failures.
3. Provision of ring arrangement for power supply in yard is in progress, spare cores are being identified to implement ring structure to avoid long duration failures in case of cable defective
4. Replacement of overaged LED is in progress, target for 2022-23 is of 1000 out of which 125 have been replaced.

MACLS

28.34%

MECH

0.10%




Source : Northern Railways / Indian Railways Portal CMS Team Last Reviewed : 07-07-2022  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.