SPECIAL WORKS DONE BY TRD DEPARTMENT 

 

CHANGES IN MAINTENANCE PRACTICES

 

S.No.

Change in Practice

1.

Foot-patrolling and footplate schedule made for supervisor and monthly monitoring of their inspections done by concerned Officer.

2.

To reduce the breakdown restoration time Mock Drills are being executed by officers in regular interval.

3.

Increase in Tower Wagon working instead of Truck movement

4.

Daily advance block planning sent to operating department for maximum utilization of block

5.

Thermo-vision checking drive launched for conditional monitoring of all joints and connectors  in the section

6.

Live Line checking of overall section has been done 2 times to arrest the failure prone areas.

7.

Condition monitoring of Transformers is being done to check the healthiness of transformer of Moradabad Division.

8.

Replacement of static panel with numerical panel was done to improve the reliability of system.

9.

Combine working of two to three tower wagons is carried out in sections where blocks are available. This maximizes the output nd helps in liquidating the maintenance of a particular section early.

10.

Maximum utilization of shadow block in NI work, Girder Launching etc.

 

 

2.System improvement-

 

 

tree trimming

211 न०

removing kite threads

175 न०

muff cleaning

287 न०