Key Targets/Objectives


To achieve zero failure in OHE

·OHE maintenance as per prevalent guide lines& RDSO maintenance instructions/Technical.

·Cutting of jointly identified dangerous tree by engineering.

·Insulator cleaning in polluted zones as per HQ office guidelines

· All efforts will be put to achieve no maintenance arrear after this financial year.

· Efforts will be put to wipe out bond deficiencies in the electrified section of the division.

·Daily advance block block planning sent to operating department to avoid maximum power block.

·Thermo-vision checking of SP/SSP/TSS and OHE section for conditional monitoring of all joints and connectors in the section/Switching posts.

·Live Line checking of overall section to be done 2 times to arrest the failures in Electrified section.

·Increase in Tower Wagon working instead of Truck movement for ladder maintenance party.

·Maximum utilization of shadow block in NI work, Girder Launching, Engineering machine block etc.

 

Target for 2023-24 is as under:

SN.

Key Performance Indicator (KPI)

Target for

2026-27

Achievement upto July-26

1

IOH of OHE single & double cantilevers (in TKM) (Frequency every 2 year)

1444

453

2

POH of ATD (Nos.) (Frequency every 4 years)

278

37

3

AOH of ATD (Nos.) (Frequency every 1years)

3719

1044

4

Checking of Turnouts and Cross-overs (Annually) as per RDSO SMI no. TI/MI/0028

1918

407

5

Checking of PTFEs (Frequency- Quarterly. Target- Total no. of PTFEsx4

204

41

6

Annual Maintenance of Section Insulators (Frequency - Yearly, Target = Population of section Insulators )

893

181

7

Annual Maintenance of Isolators (Frequency - Yearly, Target = Population of Isolators).

715

151

8

Replacing old design RRA clamps with modified RRA clamp as per Drg No. ETI/OHE/P1370-1 Rev.-F to avoid necking & parting of contact wire.

221

43

9

Live line checking by Tower wagon. Sectional Officers to accompany to cover their section in 6 months. All mainlines, excluding yard to be covered. RKM of any section to be counted when all Mainlines like UP,DN 3rd etc. are covered. (Frequency- Every six months, Target =RKM x 2)

5749

1508

10

Lubrication of SS wire rope of ATD (Frequency- Annual. Target- Population of ATD) as per RDSO SMI no. TI/MI/0029

3493

1067