Key Targets/Objectives


Key Targets/Objectives

 

 

 

                    Key Targets/Progress

 

S.No.

Items

Unit

Annual Target 2021-22

Progress for the month of Mar-22

Cumulative Progress up to Mar-22

Remarks

 

1

TRR (P)

Tkm

106.8

6.432

68.410

 

 

2

TSR (P)

Km

78.8

10.307

45.724

 

 

3

TRR (S)

Tkm

28.75

17.750

49.160

Target completed.

 

4

TSR (S)

Km

24.5

17.766

36.571

Target completed.

 

5

CTR (P+S)

CTR unit

119.43

25.905

99.933

 

 

6

Deep Screening of Plain Track

KM

170

32.981

135.200

 

 

7

Deep Screening of turnouts

Nos.

171

48

235

Target completed.

 

8

Shoulder Ballast Cleaning

KM

300

17.103

316.654

Target completed.

 

9

TTR

Eq. Nos

144

17.75

176.75

Target completed.

 

10

TWS

Nos.

30

7

46

Target completed.

 

11

TWR

KM

29

1.608

24.671

 

 

12

FBWP

Nos.

-

901

9450

 

 

13

TBR

KM

-

3.545

62.276

 

 

14

TFR

KM

250

18.610

291.890

Target completed.

 

15

TBSR

Nos.

2323

0

0

 

 

16

Rectification of defective
layout in Yards (No. of

Nos.

20

0

16

 

 

17

Ballast Supply

Lakh Cum

2.32

0.345

1.57

Including Cess supply

 

18

Ballast Inserted

Lakh Cum

2.32

0.184

1.440

 

 

19

Raising of sectional Speed

Route Km

232.19

 

106.890

Proposal of
PHR-LNK =64.10Km, JRC-HSX=38.22Km,
Total= 76.32  km Sent to HQ.

 

20

Raising of loop line speed to 30Kmph

Route Km

420.42

42.9

42.9

Proposal of
ASR-PTK =106Km,
and  ASR-KEMK =77Km,
Total= 183  km Sent to HQ.

 

21

Relaxation of PSR

Nos.

0

0

0

 

 

22

Removal of PSR

Nos.

6

1

6

 

 

23

Toe load measurement

TKM

0

25.42

220.42

 

 

24

Painting of rail

TKM

0

6.432

108.488

 

 

25

Installation of Way side lubricator

Nos.

10

0

10

Target completed.

               

 

 

 

 

 

 