Key Targets/Objectives:

 

Key targets achieved by the electrical department in 2021-22:

 

Power Supply:

 

S. No.

Description

Target

Progress

1.

Rewiring of service buildings

10 Nos.

13 Nos.

2.

Power factor improvement to unity at those locations where the units of energy in KVAH (Nos. of sub-station)

8 Nos.

9 Nos.

3.

Provision of LED based station name boards

4 Nos.

4 Nos.

4.

Provision of 5 star rating pump sets (upto 20 HP)

100 Nos.

57 Nos.

5.

Provision of escalators

4 Nos.

2 Nos.

 

Coaching:

 

S. No.

Description

Target

Progress

1.

Punctuality loss on Electrical account

0.51

0.43

2.

Enroute coach detachment

0

0

3.

Provision of 630 Amp Interlocking HOG contactor in Power cars

14 Nos.

14 Nos.

4.

Provision of safety chains for ZS coupler of LHB coaches

1024 Nos.

1024 Nos.

5.

Railmadad outstanding satisfactory feedback from customers

More than 90%

91.22%