ACHIEVEMENTS OF OPERATING (APR-JAN 2020-21)
1. Best ever loading of Foodgrain in a Month - 0.97 Million Tonnes in Oct-2020.
2. Best Ever Overall Loading in a Month – 2.15 Million Tonnes in Oct-2020.
3. Freight loading of 17.73 MT (Apr-Jan) in 2020-21 which has already surpassed Overall Loading of previous FY (17.62 MT) and also 24.07% higher than corresponding period of last year (14.29 MT).
4. Fertilizer loading improved by 23.00% over Last year (0.43 MT to 0.53 MT).
5. Automobile loading improved by 10% over LY (311 rake to 342 rakes).
6. Avg speed of freight train has been 36.87 kmph during 2020-21 (Apr-Jan), improvement of 64% against last year (22.50).
7. Delhi Division's Business Development Unit's continuous Outreach and Enhanced Engagement with Companies has resulted in Successful Introduction of several new Loadings, both in terms of Terminals as well as Commodities during April-20 to Jan-21:
8. Punctuality of M/Exp has been 93.71% in 2020-21 (Upto Jan-21), improvement of 12.20 % against last Year (83.52).
9. 12614 pair of special trains run to cater more passengers during festival rush.
10. Placement of 503 isolation coaches for COVID-19 patients at ANVT, DSJ, SSB, DEE, DEC, ANDI, DSA, TKD & PTNR.
11. Announced by Hon’ble Minister for Railways to ferry the migrants stranded across the country to their native place. Delhi Division ran 554 Shramik Special trains for distance more than 500 kms.
12. COA based caution Management system has been implemented over the Division.
13. Implementation of E-Office module and allocation of NIC mail IDs to staff along with VPN IDs to connect railnet servers.
14. IT enabled Zero Based Time Tabling through “SATSANG” software has been initiated and currently under process for planning of OD-Pair, fixation of terminals and assigning of maintenance depot in SATSANG software.
15. Post Surrendered – 20 surplus / diminishing category post (Traffic khalasi-15, Callman-3 & Box porter-2). Total money valued saved Rs. 5577600/-
16. Improvements in Goods Terminal at SHDM commissioned on 27.09.2020.
17. Greenfield PFT at Rajlu Garhi commissioned on 28.09.2020.
18. IBS between Jind – BZO (8.07 KMs) commissioned on 05.10.2020.
19. Electrification of existing Engine/Shunting line at HNZM commissioned on 18.12.2020.
20. Doubling between DBD-TPZ (27.66 KM) commissioned on 23.12.2020.
21. Extension of CSL at Nangal commissioned on 23.12.2020.
22. IBS between SPZ-KRZ (10.45 KMs) commissioned on 25.12.2020.
23. Phase-II work of Brownfield PFT at Garhi Harsaru completed on 08.01.2021.
24. Phase-II work of ICD Siding at Patli commissioned on 08.01.2021.
25. Greenfield PFT at Bhambhewa commissioned on 29.01.2021.
26. 08 Mechanical Cabins of SSB & TKD have been overhauled without minimum bare detention to trains.