         Key Targets/Objectives


 
Bookmark Mail this page Print this page
QUICK LINKS
Key Targets/Objectives

 

TARGET ACTION PLAN 2021-22 (ELECTRICAL GENERAL SERVICES)

 

S. No.

ITEMS

Target 2021-22 Yearly

Current Month

March. 22

Cumulative upto March 2022

Action to be taken

Target 21-22

Actual 21-22

1

Rewiring of quarters (Nos.)

250

0

250

252

Annual Target Met

2

Rewiring of service buildings (Nos.)

20

0

20

23

Annual Target Met

3

Energy consumption (MUs)

41.75

2.84

41.75

41.96

Increase in energy due to all Running room over the division have been made Air-conditioned and sufficient nos. of Heaters have been provided.Illumination level of all statins have been increased by providing more LED lighting.

4

Specific Energy consumption (KWH/KW/Month)

103.16

87.58

103.16

107.48

-

5

Fuel efficiency i.e. saving of HSD oil (in Ltrs) by improvement of power supply reliability.

54000

3682

54000

50523

Annual Target Met

6

Segregation of Domestic & Commercial supply to avail benefit of tariff (Nos.)

2

0

2

0

There is very small difference bet. Domestic and commercial tariff but the required infrastructure is very high hence not justified.

7

Power factor improvement to unity at those locations where the units of energy in KVAH

5

0

5

0

Power factor is better at all locations.

8

Energy Audit External (Nos.)

2

0

2

0

BTI andUMBis under planning

9

Energy Audit Internal of electrical installations at various levels (yearly)(Nos.)

 

 

 

 

 

9.1

Sr. Supervisors (Nos)

20

4

20

32

Annual Target Met

9.2

AEE/G/UMB (Nos)

2

-

2

3

Annual Target Met

9.3

Sr. DEE/G/UMB (No)

1

-

1

2

Annual Target Met

10

Use of Façade lighting with LEDs (Nos)

2

0

2

0

-

11

Provision of LED based station name boards (Nos)

5

0

5

9

Annual Target Met

12

Automation of Pumping installations with GSM technique (Nos)

50

0

50

0

Under planning

13

Provision of 5 Star rating pump sets (up to 20 HP). (nos)

25

5

25

11

Work in progress

14

Provision of Lifts (Nos) RPJ-2 Nos. in coordination with constt. & SASN-03 &UBC-01

6

2

6

3

SASN-03 completed

15

Provision of Escalators (Nos) BTI-6 nos & SIR-02in coordination with constt.

8

0

8

0

-

16

5MWpGrid connectedsolar plant by REMCL(MWp)

1.65

0

1.65

1.2 MWp

Quarterly target met

17

Joint water supply signed by Sr. DEE/G & Sr. DEN (Nos)
Stations to be decided in consultation with Sr. DEN

3

0

3

0

-

18

Half yearly joint preventive checks of Control office supply/ Equipment by Elect-G with Operating and S&T (Nos.)

2

0

2

2

Annual Target Met

19

HT panel relay testing of all 11/33 KV sub stations (nos of sub-stations)

25

0

25

0

Under planning

20

BDV testing of Transformer oil & Insulation resistance test and filtration if required for transformer (nos of transformers) nos of transformers for filtration.

95

0

95

97

Annual Target Met

21

Replacement of Overhead conductors with Underground cables.(nos of locations)

3

-

3

3

Annual Target Met

22

Replacement of Non star rated split/ window AC's with 3 star and above AC’s on age cum condition basis. (nos)

70

0

70

47

Will be replaced before summer season

23

Joint checking of RRI at Sr. DEE's level with S&T once in a year. (nos)

1

0

1

1

Annual target met

24

Half yearly Joint checking of PRS/UTS at supervisor level

550

-

550

560

Annual Target Met

25

Checking of HT crossing lines in Non-electrified section once in a year (nos)

396

-

396

397

Annual Target Met

26

Solar Units Generation per KWP/year (KWh)

1250

-

1250

945000

Annual target met

27

Provision of SMS alert system at Lifts (Nos.)

11

3

11

5

Quotation under progress

28

Provision of SMS alert system atEscalators (Nos.)

12

0

12

1

 

29

Provision of 5 Star rating equipment by venders at Railway station (Nos. of stations)

10

-

10

10

Annual Target Met

 

30

Removal of electrical fittings/solar system from the LC gates converted to ROB/RUB.

10

-

10

10

Annual Target Met

31

Surrender of sanctioned load of LC gates converted to ROB/RUB.

10

-

10

10

Annual Target Met

32

Annual checking and implementation of illumination level of Target Railway stations(Nos. of stations)

30

-

30

31

Annual Target Met

33

Quarterly Safety inspection of Lifts supervisor level

44

-

44

46

Annual Target Met

34

Half yearly Safety inspection of Escalators supervisor level

24

-

24

24

Annual Target Met

35

Net Zero Station (Nos.)

1

0

1

0

Since solar plant is on-grid type, there is no possibility for Net-Zero station.

36

Adoption of smart prepaid metering system for all Railway Installations from which Railways has to collect charges for consumption electricity.(Nos.)

300

0

300

0

 

37

To declare Railway station buildings as Green buildings(Nos.)

1

0

1

0

Solar already installed at every feasible stations.

38

To declare Railway office/Hospital buildings as Green buildings(Nos.)

1

0

1

0

Solar Water heater and solar plant installed at UMB and CDG hospital

39

Automatic Switching OFF/ON of Platforms Light for all A1/A category railwayStations (70% & 30% Circuit)

08

0

8

0

Quotation under progress

40

Improvement of illumination levels at Stations (Footfall more than 2000/day (Nos.)

12

-

12

12

Annual Target Met

 

 

 




Source : Northern Railways / Indian Railways Portal CMS Team Last Reviewed : 02-05-2022  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.