SPECIAL WORKS DONE BY TRD DEPARTMENT IN THIS FY 2022-23
S.No. | Special Work |
1. | CRS Inspection of Doubling of NERI-SPC Section (TKM:33.168) was sucessufully done on 11.04.2022 |
2. | Work of provision of Buried rail in all SP/SSP of Moradabad Division was completed |
3. | Electrification of 2 No. siding (i.e. ATLP Siding and JPL Siding of approx TKM 0.35 and 0.107 respectively) by Division itself. |
4. | Electrification of RAC Station lines and BLM Washing line was successufully done |
5. | 2 new relay Panels with Numerical relays installed at GLH/TSS, SAR/TSS because of these new panels the fault segregation has become fast and reliable. The old static relays were unreliable and less accurate. |
6. | Upgradation of SCADA system with 0130 Rev 2 has been commissioned in MB-GZB main Line section. This has increased the speed, accuracy and reliability of remote operation of switching devices during block and faults. |
7. | Tree Trimming of Approx 4753 No. of Trees were done in this Financial Year. |
8. | Replacement of 13.18 TKM of weak catenary wire in this Financial Year |
9. | Replacement of 160 mm sq G jumper in 1st Sub sector work is under progress in which 309 No. of jumper has been provided out of 536 No. of jumpers |
10. | Replacement of 36 No. of rusted cantilever in this financial year |
11. | Replacement of 95 No. of rusted ACC wire with Catenary wire to avoid failures in polluted zone |
12. | Approx 7000 No. of damaged and rusty No. plate were replaced with new No. plate. |
13. | 7260 No. of PG has been replaced in this financial year during maintenance of jumper. |
CHANGES IN MAINTENANCE PRACTICES
S.No. | Change in Practice |
1. | Foot-patrolling and footplate schedule made for supervisor and monthly monitoring of their inspections done by concerned Officer. |
2. | To reduce the breakdown restoration time Mock Drills are being executed by officers in regular interval. |
3. | Increase in Tower Wagon working instead of Truck movement |
4. | Daily advance block planning sent to operating department for maximum utilization of block |
5. | Thermo-vision checking drive launched for conditional monitoring of all joints and connectors in the section |
6. | Live Line checking of overall section has been done 2 times to arrest the failure prone areas. |
7. | Condition monitoring of Transformers is being done to check the healthiness of transformer of Moradabad Division. |
8. | Replacement of static panel with numerical panel was done to improve the reliability of system. |
9. | Combine working of two to three tower wagons is carried out in sections where blocks are available. This maximizes the output nd helps in liquidating the maintenance of a particular section early. |
10. | Maximum utilization of shadow block in NI work, Girder Launching etc. |
Electrification in Last Four Years :
S.No. | Financial Year | Electrified RKM | Electrified TKM |
1. | 2018-19 | 127.45 | 142.94 |
2. | 2019-20 | 69.4 | 156.743 |
3. | 2020-21 | 208.48 | 276.953 |
4 | 2021-22 | 105.98 | 174.53 |
5 | 2022-23 | - | 33.168 |
Total | 511.31 | 784.334 |
Electrification of Siding :
Status of Sidings of Moradabad Division |
SN | Siding | Serving Station | Section | Commodity | No. of Rakes Handled Per Month | TKM | TDC | Current Status |
RE/UMB | |
1 | IFFCO Siding | IFAB | CH-BE | Fert | 60 | 12 | 02.12.22 | EIG Under process |
2 | YARA fertilizers | TCL | CH-HGJ | Fert | 30 | 5 | 31.12.22 | 80% work completed in loading and un-loading area , Bracket erection and wiring work is under process |
Const/MB | |
3 | Jubliant Siding | GJL | MB-GZB | Coal, Fert., Container | 11 | 2.4 | 06.12.22 | Work completed , remark attending under process. EIG also processed |
4 | FCI Siding | DAM | MB-BE | Food Grain | 0.5 | 2.1 | 30.12.22 | X-over wiring is under process |
5 | FCI Siding | HPU | MB-GZB | Food grain | 0.5 | 3 | 06.12.22 | Work completed, remark attending under process. EIG UNDER PROCESS |
6 | Sugar mill siding, Dhampur | DPR | MB-SRE | Sugar | 0.5 | 0.3 | 30.12.22 | Foundation work and wiring work started but due to non availability of track fitness, work is stopped |
7 | BALLAST SIDING, Pathri | PRI | LRJ-HW | Sleeper, clinker, Container, Ballast | 15 | 1.8 | 15.12.22 | Foundation work completed. Mast erection is under process |