KEY TARGETS AND OBJECTIVES
Infrastructure Improvement
S.N. | Activity | Target 2025-26 | Achieved During month |
a | Construction of New Crew booking lobby at MB, HW & CH as per latest GAD issued by HQ. | March 2026 | MB & CH lobby Details estimate are prepared and GAD is under process. HW Lobby - Detail estimate is prepared and process under Sr.DEN/I. |
b | Construction of new running room at ROZA & YNRK including Modification of kitchen as per latest instructions issued by HQ. | March 2026 | ROZA RR - Prepare of Detail estimate is under process. YNRK RR - Currently with ED/LA Railway board Date-29/03/2025. |
c | Renovation of crew booking lobbies at HPU, LRJ & DDN as per latest GAD issued by HQ. | March 2026 | LRJ and DDN Lobby - Currently with CEPD/NR since 31.07.2025. Lobby HPU Lobby - Currently with CEPD/NR since 31.07.2025. |
d | Renovation of running rooms at HPU, NBD, BLM & DDN including modification of kitchen as per latest instructions issued by HQ | March 2026 | BLM RR - Sanctioned by GM on date - 20/06/2025. HPU and NBD RR - Currently with CEPD/NR since 31.07.2025 DDN RR - Currently with CEPD/NR since 31.07.2025. |