SPECIAL WORKS DONE BY TRD DEPARTMENT
CHANGES IN MAINTENANCE PRACTICES
S.No. | Change in Practice |
1. | Foot-patrolling and footplate schedule made for supervisor and monthly monitoring of their inspections done by concerned Officer. |
2. | To reduce the breakdown restoration time Mock Drills are being executed by officers in regular interval. |
3. | Increase in Tower Wagon working instead of Truck movement |
4. | Daily advance block planning sent to operating department for maximum utilization of block |
5. | Thermo-vision checking drive launched for conditional monitoring of all joints and connectors in the section |
6. | Live Line checking of overall section has been done 2 times to arrest the failure prone areas. |
7. | Condition monitoring of Transformers is being done to check the healthiness of transformer of Moradabad Division. |
8. | Replacement of static panel with numerical panel was done to improve the reliability of system. |
9. | Combine working of two to three tower wagons is carried out in sections where blocks are available. This maximizes the output nd helps in liquidating the maintenance of a particular section early. |
10. | Maximum utilization of shadow block in NI work, Girder Launching etc. |
2.System improvement-
tree trimming | 211 न० |
removing kite threads | 175 न० |
muff cleaning | 287 न० |